Quick Answer: The Port of Everett’s $6.75 million final-phase bulkhead and wharf rebuild — the project running along West Marine View Drive at Port Gardner Landing — is on track to wrap by May 2026 after starting in early September 2025. Bergerson Construction is replacing roughly 165 lineal feet of aging wooden bulkhead with steel piles to stabilize State Route 529 above it, and the wharf overhead is getting fresh decking, ADA-compliant trail connection, and new landscaping. It is the last piece of a 20-year bulkhead replacement effort that has quietly been holding the marina in place for two decades.
The $6.75M Wharf Rebuild on West Marine View Is About to Finish — Here’s What 20 Years of Bulkhead Work Looks Like When It’s Done
If you’ve driven southbound on West Marine View Drive any time since last September and wondered why one lane has been closed near Port Gardner Landing and the Grand Avenue Park Bridge, the answer is the most quietly important construction project on the Everett waterfront. The Port of Everett’s final phase of marina bulkhead replacement and wharf rebuild — a $6.75 million contract awarded to Oregon-based Bergerson Construction — is on schedule to complete in May 2026. After 20 years of bulkhead work, segment by segment, this is the piece that finishes the system.
It is not the splashiest project on the waterfront. It does not come with a ribbon cutting and a brewery opening. But it is the structural reason the road above it stays put, and the reason the marina behind it does not slowly slide into Port Gardner Bay. So we walked the project, read the contracts, and figured out what May actually means.
What’s Actually Being Replaced
The project is doing two things in one footprint:
Segment E bulkhead. The Port is pulling out approximately 165 lineal feet of aging wooden bulkhead and driving steel piles in its place. That bulkhead is the engineered wall that separates the marina from the highway above it. It is the reason State Route 529 — better known locally as West Marine View Drive — has not subsided into the water. The original wooden structure is decades old. Steel piles will hold the same line with significantly more long-term stability and capacity to support the corridor above.
Wharf reconstruction. Directly above the bulkhead, the section of overwater wharf is being torn out and replaced with new decking. New landscaping is going in alongside it, and the rebuilt wharf will tie into the Port’s waterfront trail system with an ADA-compliant connection — closing a long-standing accessibility gap on the trail. Pedestrian separation from the busy roadway is part of the design, which matters on a corridor that carries commuter, freight, and military traffic in and out of Naval Station Everett.
Why SR 529 Is the Real Story
The official name of the project — “Segment E Wharf and State Highway 529 Stability Improvements” — buries the lead. This is a stability project for a state highway as much as it is a marina project. SR 529 / West Marine View Drive is the spine of the Everett waterfront. It connects downtown to the Port, to NAVSTA Everett, and to the freight and military supply chain that runs through the seaport. The wooden bulkhead that has been holding it up was placed before most of the apartments at Waterfront Place were even drawings. It earned its retirement.
The Washington State Department of Transportation is a stakeholder in the project for the same reason. Anything that happens to the bulkhead happens to the roadway. Replacing 165 LF of aging wood with engineered steel piles is the kind of unsexy infrastructure investment that quietly extends the design life of a critical regional corridor by decades.
Why This Is the End of a 20-Year Project
The Port has been replacing bulkhead segments along this stretch of waterfront in phases for two decades. Each segment has been a distinct contract, a distinct construction window, and a distinct round of permitting with state and federal regulators. Segment E is the final phase. When Bergerson hands the keys back to the Port in May, the bulkhead replacement program — the one that has been running quietly underneath every photo of the marina since the early 2000s — is structurally complete.
That matters because the next 20 years of waterfront development at Waterfront Place — the 660 housing units at full build-out, the 447,500 square feet of office, the two hotels, the 63,000 square feet of retail and restaurants — all sit on top of, or directly behind, a marina that is now backed by modern bulkhead the entire length of Segment A through E.
The Lane Closure Story
The construction has required southbound lane closures on West Marine View Drive in the work zone, with traffic reduced to one lane in the affected section. Public access to the trail in that area has also been re-routed during the work window. If you have been driving north-south through the Port and noticing the cone line near Grand Avenue Park Bridge, that is the project. The lane closures end when the project ends — May 2026 is the target.
How the Project Connects to the Port’s $70M 2026 Budget
The Segment E work is being delivered out of the Port’s preservation and maintenance budget rather than its capital expansion budget. The Port Commission’s adopted $70 million 2026 budget — covered in our breakdown of what Everett’s waterfront is actually getting this year — sets aside $7.1 million for maintenance and preservation, including pier strengthening, marina bulkhead work, boat launch updates, and dredging. The Bergerson contract was awarded in May 2025, so Segment E is largely a 2025-funded project crossing into 2026, but the maintenance posture that allowed it sits squarely in the 2026 budget posture as well.
That posture matters for residents and tenants. The Port is funding both the new buildings — $2.6 million in the 2026 budget for new public infrastructure and Waterfront Place retail and restaurant buildings — and the unglamorous work of keeping the existing marina structurally sound. Segment E is the second category.
What Changes for Trail Users in May
For everyday waterfront users, the most visible change in May will be the trail itself. The new ADA-compliant connection through the rebuilt wharf section closes a gap that has frustrated wheelchair users, stroller pushers, and anyone using the waterfront trail for the full distance. New landscaping, new decking, and a designed pedestrian separation from the roadway will turn what is currently a construction zone into a finished section of trail. The kind of walk that has been awkward for two decades — past wood pilings, narrow paths, and an unfinished feel — gets rebuilt to the standard the rest of the waterfront has been moving toward.
What Comes Next
With the bulkhead done, the next major Port construction milestone in the pipeline is the Jetty Landing renovation, which is anticipated to begin in 2027 per the Port’s 2026 budget plan. The Eclipse Mill Park Riverfront work — covered in our piece on why Everett’s riverfront signature park is now a spring 2028 opening — runs on its own timeline, with Phase 1 (City) running July to November 2026 and Phase 2 (Shelter Holdings) running fall 2026 through spring 2028. And the West Marine View Drive pipeline project — the $113 million combined sewer, stormwater, and water-main replacement we covered when council approved it April 2 — kicks off later this year just a few hundred feet north of where Bergerson is finishing up. The order of operations is intentional: stabilize the bulkhead, then dig the pipeline, then build the buildings.
Frequently Asked Questions
What is the Segment E bulkhead and wharf project?
It is a $6.75 million Port of Everett construction project replacing approximately 165 lineal feet of aging wooden bulkhead with steel piles along West Marine View Drive at Port Gardner Landing, near the Grand Avenue Park Bridge. The overwater wharf above it is also being rebuilt with new decking, an ADA-compliant trail connection, and new landscaping. Bergerson Construction is the contractor.
When does the project finish?
Construction began in early September 2025 and is targeted for completion in May 2026.
Why does this affect State Route 529?
The bulkhead structurally supports the embankment that holds State Route 529 / West Marine View Drive in place. Replacing the aging wooden structure with steel piles stabilizes the highway corridor above the marina for the long term.
Will the lane closures end when the project ends?
Yes. The southbound single-lane configuration on West Marine View Drive in the work zone is in place for the duration of construction and ends when Bergerson completes the project in May 2026.
Is this part of Waterfront Place?
Geographically yes — the work site is along the same waterfront corridor — but the project is funded out of the Port’s preservation and maintenance budget, not the Waterfront Place capital build-out. It is the unglamorous structural work that keeps the marina in place while the new buildings go up around it.
Does the rebuilt wharf improve the waterfront trail?
Yes. The new wharf section will include an ADA-compliant connection to the Port’s waterfront trail system, closing a long-standing accessibility gap, plus new landscaping and pedestrian separation from the roadway.
Is this the last bulkhead replacement project?
Yes. Segment E is the final phase of a roughly 20-year, segment-by-segment bulkhead replacement program along this stretch of the marina. When Bergerson finishes in May, the program is structurally complete.